MARINE ENGINEERING SPECIALIST

Bio Marine Ingredients

Project Details

In 2016, KER were awarded the contract for the main contract build of this new factory for Bio Marine Ingredients Ltd.

Works completed

Overview:

  • Installation of process equipment.
  • Installation of electrical works.
  • Installation and welding of all pipework to the process equipment and all other factory needs (pressure washer system, fire hose, sinks, eye wash points).
  • Installation and fine tuning of wastewater treatment plant.

Process Equipment: 

  • Over 90 pieces of equipment installed
  • The process installation was separated into 4 areas: Intake area, wet process area, evaporator area & miller drier room.
  • Intake area: Conveyor belt, mincer & mixing tank
  • Wet process area: 1st floor: 9 x plate heat exchangers, 28 x pumps, 14 x stainless steel tanks with the largest 6m in height. 2nd floor: 4 x plate heat exchangers, 2 decanters, 3 x separators, 2 x flow heat exchangers & 1 pump.
  • Evaporator area: A 9m evaporator, 2 x filter skids (membrane filtration & nano filtration) , 6 x pumps & a vacuum pump
  • Miller drier room: 2 x filtration tanks, a bone hopper (which extracts bones from fish liquidized mixture), an ultra rotor (turns liquid into powder which uses a gas boiler as a heat source) and a ventilator.

Electrical: 

  • New light system controlled by a PLC.
  • Supply to process equipment, wastewater treatment plant and office areas including canteen, board room and changing rooms.

Pipework:

  • Total contract included 2.7km of stainless steel piping & 1400 purged welds, all supported and bracketed to prevent vibration.
  • Mild steel & plastic pipework also completed by our team.
  • Majority of the S/S pipework was completed in the wet process area, evaporator area and in the main headers on the pipe bridge.

Wastewater Treatment Plant:

  • Large tank 30m³ installed and sealed fully.
  • Scraper installed to filter the incoming waste water to prevent solids entering the main tank.
  • A Dissolved Air Flotation (DAF) which takes solids out of the water was installed and calibrated. It was calibrated to ensure the PH Level of 7 before the cleaned water was sent to County Council Water Treatment Plant.
  • Dosing Pumps were installed to regulate the PH of the Wastewater.

 

Client: Bio Marine Ingredients Ltd.
Location: Castleblayney, Monaghan, Ireland